| Community Budget Issue Requests - Tracking Id #3359 | ||||||||||||||||
| Erosion Control Measures for Bishop Creek at Rainbow Farms | ||||||||||||||||
| Requester: | Kimberley O. Tracy, P.E. | Organization: | City of Safety Harbor | |||||||||||||
| Project Title: | Erosion Control Measures for Bishop Creek at Rainbow Farms | Date Submitted | 1/13/2006 4:40:08 PM | |||||||||||||
| Sponsors: | Berfield | |||||||||||||||
| Statewide Interest: | ||||||||||||||||
| The project will address water quality from a tributary of Tampa Bay. By reducing the erosion to the creek banks, the amount of sediment reaching the Bay should be reduced. | ||||||||||||||||
| Recipient: | City of Safety Harbor | Contact: | Kimberley O. Tracy, P.E. | |||||||||||||
| 750 Main Street | Contact Phone: | (727) 724-1555 | ||||||||||||||
| Safety Harbor 34695 | Contact email: | ktracy@cityofsafetyharbor.com | ||||||||||||||
| Counties: | Pinellas | |||||||||||||||
| Gov't Entity: | Yes | Private Organization (Profit/Not for Profit): | ||||||||||||||
| Project Description: | ||||||||||||||||
| Construction of erosion control measures (to be determined in design phase currently being performed) along Bishop Creek at Rainbow Farms to reduce further erosion. | ||||||||||||||||
| Is this a project related to a federal or state declared disaster? | No | |||||||||||||||
| Measurable Outcome Anticipated: | ||||||||||||||||
| Project is anticipated to reduce sediments into Tampa Bay as well as protect property/structures along the creek. | ||||||||||||||||
| Amount requested from the State for this project this year: | $500,000 | |||||||||||||||
| Total cost of the project: | $1,000,000 | |||||||||||||||
| Request has been made to fund: | Construction | |||||||||||||||
| What type of match exists for this project? | Local | |||||||||||||||
| Cash Amount | $500,000 | |||||||||||||||
| Was this project previously funded by the state? | No | |||||||||||||||
| Is future-year funding likely to be requested? | No | |||||||||||||||
| Was this project included in an Agency's Budget Request? | No | |||||||||||||||
| Was this project included in the Governor's Recommended Budget? | No | |||||||||||||||
| Is there a documented need for this project? | Yes | |||||||||||||||
| Documentation: | Safety Harbor Stormwater Master Plan and Bishop Creek Erosion Control Study. | |||||||||||||||
| Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? | Yes | |||||||||||||||
| Hearing Body: | Safety Harbor City Commission | |||||||||||||||
| Hearing Meeting Date: | 11/07/2005 | |||||||||||||||
| Is this a water project as described in Section 403.885, Laws of Florida? | Yes | |||||||||||||||
| Has the project been submitted to the Department of Environmental Protection? | No | |||||||||||||||
| Is this project eligible under section 403.885(5) F.S.? | Yes | |||||||||||||||
| Is your project addressed in a state, regional or local plan (such as a SWIM plan, Comprehensive Plan, local master plan, etc.)? | Yes | |||||||||||||||
| Name the plan and cite the pages on which the project is described: | ||||||||||||||||
| Safety Harbor Stormwater Master Plan, pages 70-74. | ||||||||||||||||
| If you are requesting funding for a stormwater or surface water restoration project: | ||||||||||||||||
| Which Water Management District has the jurisdiction of your project? | ||||||||||||||||
| Southwest Florida Water Management District | ||||||||||||||||
| Have you provided at least 50% match? | Yes | |||||||||||||||
| Match Amount: | 500000 | |||||||||||||||
| Match Source: | Safety Harbor/SWFWMD | |||||||||||||||
| Will this project reduce pollutant loadings to a water management district designated 'priority' surface water body? | Yes | |||||||||||||||
| Name of water body: | Tampa Bay | |||||||||||||||
| Describe how it will reduce loadings, identify anticipated load reductions for total suspended solids, total nitrogen, total phosphorus, and other contaminants, and specify the practices that will be used to reduce loadings: | ||||||||||||||||
| Existing Bishop Creek cross sections will be widened and planted with native plants for the entire improved cross sections. This will result in reduced stream velocities and sediment loads, and increase pollutant (N,P,others) uptake. | ||||||||||||||||
| If you are requesting funding for a wastewater project: | ||||||||||||||||
| Does your project qualify for funding from DEP's 'Small Community Wastewater Treatment Grant Program' under section 403.1838 F.S.? | No | |||||||||||||||
| Other wastewater projects: | ||||||||||||||||
| Have you received previous legislative funding for this project? | No | |||||||||||||||
| Is the project under construction? | No | |||||||||||||||
| Have you provided at least a 25% local match? | No | |||||||||||||||